The planning department of an electronics firm has set up the activities for developing and production of a new MP3 Player. Consider the information in the table below.
Activity ID Description Activity Predecessor Activity Time (weeks) 1 Staff None 2 2 Develop market programme 1 3 3 Select channels of distribution 1 8 4 Patent 1 12 5 Pilot production 1 4 6 Test market 5 4 7 Ad promotion 2 4 8 Set up for production 3,4,6,7 16
2.1 Develop a project network diagram (AON). (8 marks)
2.2 Determine the early start, early finish, late start, late finish and slack for each activity
(16 Marks)
2.3 Identify the critical path.[assignment ]The planning department of an electronics firm has set up the activities for developing and production of a new MP3 Player. Consider the information in the table below.