Explain the difference between value-added and non-value-added activities. 1 answer below »
(Activity analysis; MCE) Log Cabins Unlimited constructs vacation houses in the North Carolina mountains. The company has developed the following value chart:
Average Number
Operations
of Days
Receiving materials
2
Storing materials
10
Measuring and cutting materials
9
Handling materials
7
Setting up and moving scaffolding
6
Assembling materials
3
Building fireplace
12
Pegging logs
8
Cutting and framing doors and windows
5
Sealing joints
4
Waiting for county inspectors
6
Inspecting property (county inspectors)
1
a. What are the value-added activities and their total time?
b. What are the non-value-added activities and their total time?
c. Calculate the manufacturing cycle efficiency of the process.
d. Explain the difference between value-added and non-value-added activities.