All of the following statements, except 1, are correct responses regarding the work breakdown str…

All of the following statements, except 1, are correct responses regarding the work breakdown structure (WBS) for a project. Identify the 1 INCORRECT statement from the list below. The WBS provides the preliminary, deliverable oriented approach to the project The WBS decomposes the work to be executed by the project team. The WBS, once defined and baselined, will remain constant throughout the project The WBS represents a decomposition of tasks, from a summary level, down to an “actionable1 task that will be assigned to a resource(s) to accomplish. The WBS provides the overall “task list” of a project, but does not include the other “schedule items” such as resource assignments or task durations.